Engineering Maintenance Department: Completion of the first stage of the Sixth Hayat Lobby in Al-Muthanna Governorate

The staffs of the Engineering Maintenance Department in the al-Abbas's (p) Holy Shrine have completed the first phase of the Sixth Hayat Lobby project for treating people infected by the Corona virus in Al-Muthanna Governorate, by the completion of preparing the ground on which the project will be built, which covers an area of ​​(3500) square meters by 100%.
The engineer of the project, Safaa Mohamed Ali, explained to the al-Kafeel Network: "With continuous work for late hours of the night, the first stage of this project has been completed, according to the technical specifications approved by the beneficiaries."
Noting: "The remaining space that was accomplished was related to the space allocated to the main entrance and the rooms of doctors and the pharmacy, and thus the first stage that is considered one of the most important stages has been completely completed, and we will proceed to install the iron structure."
He added: "The work for the other stages is conducted in parallel and at the rate of (12) working hours, in order to complete the project within the specified timings, and among these works:
- Starting the work on the drainage points linking sewage pipes.
- Working on covering the floor of the bathrooms in each room, and working on completing the foundations for the sanitation of the remaining ones.
- Continuing electrical supply work.
- Continuing cutting work that has reached a completion rate of more than (90%)."