The engineer of the project, Safaa Mohamed Ali, explained to the al-Kafeel Network: "The work stages go in parallel without intersection and have progressed significantly, as the work being done now includes:
- Starting dyeing works for the rooms' walls.
- PVC Windows installation work.
- Starting the work of secondary roofs.
- Fixing the PVC partitions for (114) single rooms.
- Works of laying water pipes for bathrooms in all rooms.
- Installing water heaters for each room.
- Firefighting system works.
- Working to complete the sanitation facilities.
- AIR FRESH cooling system parts are installed.
- Continuing electrical supplies and wiring works.
- Paving the spaces between the parts of the building with concrete paving blocks (muqarnas) 100%.
- Completion of bathrooms' flooring works for (114) single rooms.
- Completion of covering the walls with gypsum board.
- Completion of the cutting work.
- Achievement of the erection of the iron structure.
- Completion of pouring concrete foundations."