Escalating pace of work in the Seventh Hayat Building project in Babylon Governorate.

Rising levels of work are witnessed in the seventh building for the treatment of people affected by Corona virus in Babylon Governorate, which is being carried out by the cadres of the maintenance and engineering construction department at the al-Abbas's holy shrine, within the Marjan Medical City in the governorate, in order to complete it within what is technically and medically planned.
The engineer of the project, Ammar Salah, explained to the al-Kafeel Network: “The works in the project are proceeding according to what is planned for them, and we have reached this percentage, which will witness a significant increase in the coming days, thanks to the efforts made by the working staff, who were not affected neither with what surrounds them as they are working in the proximity to the isolation lobbies, nor by the weather conditions as a result of high temperatures. Rather, these conditions and others formed an incentive for them to implement all the project parts that are witnessing remarkable progress day after day."
He added, "The works are currently being carried out on the three parts of the project, which total area is (3500) square meters and includes (98) single rooms, in addition to more than (25) rooms that varied between medical, administrative and service rooms."
Regarding the most important percentages achieved by the staff working in this project, he stated: “The work currently underway is to install the cooling devices with external parts (split units), while continuing to install and fix the conveyor sections (ducts) for the two systems of fresh air and discard polluted air, and wiring the alarm and fire alarm systems.
He added, "There are also other works that are being carried out, such as establishing the medical oxygen system, cladding the floors of bathrooms with ceramic material for single rooms and fixing their walls, in addition to cladding the corridors separating the three parts of the project and surrounding buildings."
As for the work of the electrical system, Eng. Ammar explained: “The work of wiring this system is continuous according to the loads specified for it, and is carried out in parallel to the aforementioned work of installing the insulating sections on the walls of the building (Gypsum Board), which is nearing completion in addition to the work of installing the doors and windows. "