The staff of the Engineering Maintenance Department is soon completing the first phase of the maintenance and development campaign for some parts of Karbala Teaching Hospital for Children.

The staffs of the Engineering Maintenance Department at the al-Abbas's (p) Holy Shrine continue their comprehensive campaign to maintain and develop some parts of Karbala Teaching Hospital for Children, as they are close to the completion of the first phase of this campaign.
Engineer Mohammed Al-Taweel explained to the al-Kafeel network, saying: "Work is going on in the Karbala Teaching Hospital for Children, through the rehabilitation and maintenance of all bathrooms affiliated with the hospital, in addition to covering floors, as well as painting works."
He added: "We are close to the completion of the first stage, which includes maintenance and rehabilitation of three bathrooms, as the completion rate within this stage reached 75%."
He explained: "We divided the work into four phases according to what is planned, so that all bathrooms in all hospital departments can be maintained and developed, in addition to other actions such as covering the floors and painting the walls, and all of this will be done according to the specifications and standards required from Hospital administration".