With an increasing pace and a high concern derived from the source of generosity and benevolence; Aba Al-Fadl Al-Abbas (peace be upon him), the staff working in the project of the second educational cultural complex, which is located on the road of (Karbala - Al-Hur), continue their efforts at advanced levels that exceeded (65%).
This was confirmed to the al-Kafeel Network by the head of the engineering projects department of the al-Abbas's (p) Holy Shrine; Eng. Diaa Majeed Al-Sa'egh, and he added: “The educational complex projects are among the important projects implemented by the Holy Shrine, which have given them great attention, so their work has not been stopped or delayed, but goes within the timelines and engineering specifications prepared for it, including the second educational complex, in which we have reached this percentage for the stage of completion in its work, which is conducted in parallel lines and according to the detail of each work. "
Noting: "The works fall within the second stage of this project, which was initiated after taking the fundamental approvals for its implementation."
He explained: "One of the most important works currently underway is the installation of (acoustics - alarm - fire - monitoring - lighting ... and others) systems, in addition to the work of the infrastructure of the project and the cladding work of external and interior walls and fixing doors and windows, and other work that falls within the stages of mechanical, urban and electrical finishings.
It is worth noting that the project of the second education and teaching complex is one of the most important projects of the al-Abbas's (p) holy shrine for its strategic dimension to complement the first and third complexes. It is located on the road Karbala - al-Hurr.
The project is established on an estimated area of 10.710 square meter. The facilities of this group include:
- Two schools for boys with classrooms, labs and other educational facilities in three floors on a total area of 2400 m2.
- A kindergarten on an area of 1250 square meter also in three floors.
- Sports hall of multiple uses on an area of 1300 square meter.
- A school for girls on a total area of 2400 square meter
- Gardens and main and sub- roads.