Infrastructure reaches completion rate (90%) for the Lobby Project for the reanimation of patients with Corona at Al-Hindiya Hospital.

"The infrastructure works in the lobby have reached a completion rate of (90%), and they are carried out in parallel lines with other works," explained the engineer carrying out the lobby project for the reanimation of the patients with Corona at the Al-Hindiya General Hospital.
He added: "Basic cutting work, fixing the (sandwich panel) sections and covering them with gypsum board sections have been accomplished 100%."
Noting: "The technical staff in the Electricity Division of the Engineering Maintenance Department - which is the executing party of the project - started electrical wiring and delineated paths according to the approved plans."
Adding: "PVC windows and doors work in the Engineering Maintenance Department workshops is proceeding with an increasing frequency, in order to prepare it to be installed in the places that were previously prepared, in addition to the continued dyeing work that includes the basic layers."
It is noteworthy that the place where the hall is built is an open concrete structure designed for other purposes, so the first stages of work were cutting the area (1500 square meters) into large isolated halls, according to a plan approved by the beneficiary.