Engineering Maintenance Department: Completion of 70% of the Iron Structure of Sixth Hayat Hall in Al-Muthanna Governorate

The staffs of the Engineering Maintenance Department at the al-Abbas's (p) Holy Shrine completed 70% of the Iron Structure of the Sixth Hayat Lobby Project, to treat those with corona virus in Al-Muthanna Governorate.
The engineer of the project, Safaa Muhammad Ali, explained to the al-Kafeel Network, saying, "The percentage of completion of the iron structure has reached advanced stages, as the iron structure of the first and second sections has been completed and work is underway in the third segment."
He added, "Our technical staff in the plumbing unit started the works of infrastructure for the 114 single rooms (suites), by laying sewage pipes. And the completion rates reached 30%."
Stressing: "The work of separation with "Sandwich Panel" is still continuing, as it reached a completion rate of 40%, and the electrical work of the rooms is being carried out with it."