Engineering Maintenance Department: Achievement of 85% in the steel structure and the (Sandwich Panel) for the Sixth Hayat Lobby in Al-Muthanna Governorate.

The staffs of the Engineering Maintenance Department at the al-Abbas's (p) holy shrine completed 85% of the iron structure of the Sixth Hayat Lobby project for treating people with corona virus in Al-Muthanna Governorate, while the work of the (Sandwich Panel) reached a completion rate of 85% as well.
The engineer of the project, Safaa Mohamed Ali, explained to the al-Kafeel Network: "The remaining percentage of the achievement rates for the steel structure, is what is left of the areas allocated for the main entrance and the rooms of doctors and the pharmacy."
He added, "The work is carried out in parallel to the other stages, as work is still ongoing with electrical supplies, in addition to completing the connection of the main pipe of the sewage."
Stressing: "The work is conducted at a rate of (12) working hours, in order to accomplish the project within the specified timelines, and within the approved specifications."