In Pictures: The work progress of the Fifth Hayat Building to treat those affected by the Corona virus in Baghdad.

Work is proceeding on the Fifth Lobby project for treating people affected by the Corona virus in the capital, Baghdad, within what is planned in time and implementation and according to the specifications prepared for it, as the staff of the Engineering Maintenance Department of the al-Abbas's (p) Holy Shrine make every effort for this humanitarian purpose.
One of the engineers of the project, engineer Ali Al-Har has explained to the al-Kafeel Network: “The first part of the project of the installation of the (sandwich panel) sections has reached more than 40%, and the works have reached the ceiling stage after most of the walls of this part have been completed, Which has an area of ​​(1377) square meters with (56) single rooms. And starting the preparation for fixing its doors and windows, as the iron frames on which they will be installed, have been completed, after being manufactured in the department's workshops in the Karbala Governorate ".
He added: "This part also witnessed the preparation of the bathrooms' flooring of the rooms for the purpose of cladding it with ceramics, as well as the completion of most of the infrastructure, by laying sewage pipes and connecting them to the main pipes."
With regard to the second part, Al-Har indicated that: "All of its iron sections have been prepared, after taking the measurements of the (56) single rooms, and their installation will be started as soon as possible, God willing, and with regard to the third and final part, it has been prepared completely for the purpose of initiating the work of casting concrete foundations. "
Readers' comments
No comment
Add a comment
Name:
The country:
Email:
Share: