Engineering Maintenance Department: Completion rate of the Sixth Hayat Lobby in Al-Muthanna Governorate reached 50%.

The engineering and technical staff working in the Sixth Hayat Building project for treating people with Corona virus, which is implemented by the engineering maintenance department staff of the al-Abbas's (p) holy shrine for the Department of Health in the province of Muthanna, announced that the completion rate of the project in all its stages reached 50%, with work continuing in most parts for more than (12) hours a day.
The engineer of the project, Safaa Mohamed Ali, explained to the al-Kafeel Network: "After completing the preparation of the ground on which the project will be built, which has an area of ​​(3500) square meters, and the works are progressing in the other stages in an overlapping manner, the project reached a completion rate of 50%."
He added, "The works of the other stages are conducted in parallel with other works that included:
- The completion of the installation of the iron structure by 85%.
- 100% completion of pouring concrete foundations.
- Starting pouring drainage points linking sewage pipes.
- Working on covering the floor of the bathrooms for each room, and working on completing the sanitation facilities for the remaining ones.
- Continuing electrical supply work.
- Continuing cutting works that have reached a completion rate of more than (90%)."