The Sixth Hayat Building for Coronavirus Treatment in Al Muthanna Governorate has reached an achievement rate of 95%.

The work of the cadres of the maintenance and engineering construction department at the al-Abbas's (p) Holy Shrine, in the Sixth Hayat Building project for treating people with the Coronavirus, reached 95%.
The project manager, Eng. Imad Habib Hashem, told Al-Kafeel Global Network, saying: “The work continues for late hours to complete the project within what is planned in time, technically and medically, as it is built on an area of ​​(3500) square meters, and includes (114) single rooms, in addition to medical, administrative and service rooms, and bathrooms. "
He affirmed: “The works that have been accomplished in recent days are:
- Completion of the installation of the PVC windows.
- Completion of dyeing work.
- Completion of secondary roofing works.
- Completion of the installation of PVC sections for (114) single rooms.
- Completion of laying water pipes for bathroom units in every room.
- Completion of wall covering with (gypsum board).
- Completion of installing water heaters for each room.
- Completion of the fire extinguishing system.
- Completion of cladding the bathroom floor for each room, and work to complete the sanitation foundations for the remaining ones.
- Completion of the installation of the parts for the fresh air intake system (AIR FRESH).
- Completion of electrical supplies and connections.
- Accomplishing the paving of spaces between the parts of the lobby with concrete paving bricks (Muqarnas).
- Completion of cutting work, which reached 100%.
- 100% completion of the erection of the iron structure.
- 100% completion of the pouring of concrete foundations.

Indicating: "Thus, the project has reached its final stages, leaving nothing but the floor of the building that we started to complete, which will be of (epoxy) against bacteria."